Road Construction on River Road from Memorial Hill to 600 North has begun in earnest. The Road will be closed from Memorial Hill to 600 North during this time.

Landmark Excavation will be starting a construction project that consists of a new water line, power conduits, and road reconstruction that started on February 17, 2020 pm River Road from Memorial Hill to 600 North. The detour route will have traffic go up 100 north to Center Street then to 600 north and back to River Road.
During this time people who live on River Road will have access to their homes, school buses, EMS, Fire, and Police will have access though the site. Landmark has coordinated with Wasatch County School District Bus garage on access. All traveling public will need to follow the detours. There will be accommodations for people who want to park and walk Memorial Hill. They will need to follow the path that will be set up by the contractor to access Memorial Hill.
The new water line install should take approximately 3 weeks.